Project Object Budget Amount

   3212 ‐ Capital Improvements 2020                                                                                                                                        Revenue

0000 ‐ Pasco County School District

99999 ‐ Fund Balance

4996 ‐ Restricted Fund Balance

1,775,052

Revenue Total


1,775,052

Appropriations

0121 ‐ Shady Hills Elementary 85200 ‐ Re‐Roofing


5600 ‐Capital Outlay


191,732

0351 ‐ Fox Hollow Elementary 85200 ‐ Re‐Roofing


5600 ‐Capital Outlay


1,583,320

Appropriations Total


1,775,052


image

Project Object Budget Amount

 

3422 ‐ PECO 21‐22 3611 ‐ CO & DS 3929 ‐ COPS 2018A 3932 ‐ COPS 2020C 3981 ‐ S&S 19‐20 3982 ‐ S&S 20‐21